Duval County I-95/I-10 Interchange

Owner:
Florida Department of Transportation
Location:
Jacksonville, Florida
Architect:
URS Corporation
Contract Value:
$150,000,000
Completion Date:
November 2010
The improvements under this contract consisted of the construction of the interchange between Stockton St.(I-10) and Fuller Warren Bridge to Adams St.(I-95). Included are 17 Bridges and 600,000 CY of embankment to rebuild a major interchange between two interstates in Jacksonville. This project also includes new roadway construction, drainage, signing and pavement markings, drainage ponds, and other incidental construction items along with bridge painting of the approach spans, the existing trestle bridge over Myrtle Avenue, the Jacksonville FDOT Urban Office Parking Lot, and first floor building renovations.